YTC PROJECT REFERENCE
Budweiser Wugang: relocation, purification and recovery upgrades
Our project register records a 2018 AB InBev Brewery Wugang project in Hunan, China, at 1,000 kg/h.

| Reference element | Recorded basis |
|---|---|
| Source / application | Brewery |
| Product specification | Food-grade, purity ≥99.998% |
| Record IDs | 65, 84 |
A reference that includes plant modernization
Our project register records a 2018 AB InBev Brewery Wugang project in Hunan, China, at 1,000 kg/h. The stated EPC scope includes a complete CO₂ recovery system with relocation and purification retrofit of an original Haffmans system. The register specifies food-grade CO₂ with a design purity of at least 99.998%.
A separate 2021 Wugang entry records a 1,200 kg/h energy-efficiency and purification retrofit. Both entries are retained. They describe different reference scopes and should not be merged into an invented single capacity or interpreted as a measured before-and-after performance result.
Why a relocation is an engineering project
Moving an existing recovery system involves more than reinstalling the equipment in a new arrangement. A comparable relocation requires a condition review, a new utility and connection plan, and checks that the retained equipment still suits the intended gas source and product requirement. Existing vessels, compressors, refrigeration equipment and controls may have different remaining service needs.
The Wugang record is useful because it explicitly connects relocation with purification work. For a buyer, that suggests the importance of reassessing the process route during a move, rather than assuming that the original configuration automatically meets the new operating objective.
Defining the purification upgrade
A brewery’s quality requirement should describe oxygen, moisture, odour-related compounds and other specified impurities as well as overall CO₂ purity. When upgrading an installed system, the investigation should trace where unwanted components enter and how each treatment stage performs. Gas analysis, condensate handling, adsorbent condition and regeneration arrangements can all influence the assessment.
The purpose is to identify the limiting duty before selecting modifications. A targeted change to purification may be more relevant than replacing unrelated equipment. The final scope must still consider how the modified section affects pressure drop, refrigeration load, control sequences and downstream liquid quality.
Integrating retained and new equipment
The source identifies the original system brand to describe the installed equipment context. It does not imply an endorsement or an authorized-service relationship with that manufacturer. The engineering question is whether the retained equipment and the new scope can work together safely and consistently under the agreed operating conditions.
For a similar retrofit, we need equipment lists, available drawings, operating trends and recent product analyses. The integration review can then define mechanical connections, instrumentation requirements, interlocks and acceptance tests. Production scheduling is also important because tie-ins and commissioning need to fit the brewery’s available shutdown window.
Relevance to an overseas brewery
Wugang is a particularly useful reference for breweries that already own CO₂ recovery equipment and want to assess relocation, purification improvement or a future expansion. The documented 2018 and 2021 scopes show why an equipment partner should understand both complete systems and focused modernization work.
An effective enquiry starts with the present capacity, observed constraints and the desired operating outcome. Share the existing gas and product analyses, equipment age, utility limits and planned production changes. We can then separate equipment that can remain in service from duties requiring modification and propose a clearly bounded upgrade. Any promised quality, capacity or energy result should be established in the project specification and demonstrated through the agreed acceptance procedure.
Reference & evidence notes
Recorded capacity and quality values are source specifications, not independently verified operating output. Engineering discussion explains the application; it is not a reconstruction of unrecorded project details.
START WITH YOUR SOURCE
Discuss a project with a comparable source and scale.
Send your gas analysis, flow profile, product target and project location. We will help connect the technical questions with a practical supply scope.